You signed in with another tab or window. Reload to refresh your session.You signed out in another tab or window. Reload to refresh your session.You switched accounts on another tab or window. Reload to refresh your session.Dismiss alert
Describe ways the team or process can improve here
Delayed sprint close by a couple days again; time spent catching up on AI is fine, but I likely spent too much time planning other features – plan only what you can accomplish, otherwise work is just piling up. Fortunately (or not) the planning was on another project, so it's not like it's causing rework on this project. Even if I get distracted by more exciting projects, we should go ahead and close an iteration on schedule even though no one is counting on us :P
Get a teeeam
The text was updated successfully, but these errors were encountered:
TSampley
changed the title
Sprint Review - Iteration <Number>
Sprint Review - Iteration 7
Oct 2, 2024
Iteration 7 - Alpha
What was delivered
Attach completed issues here
Sprint Demo
Attach screen recordings of feature demos or link to reports
What was not delivered
Attach issues not completed below
In progress
Not started
Improvements
Describe ways the team or process can improve here
The text was updated successfully, but these errors were encountered: