  • Week 1: 23/05/2017 to 28/05/2017

    • Did some research on existing Modular Robots and planned our approach.
    • Added report on project approach. Resources can be found here: https://goo.gl/4ZXmfM
    • Tested the components given: Servo SG90, Bluetooth Module HC05, Arduino Nano, 1s 500mAh LiPos and Sharp IR GP2Y0A21.
    • Added Wiki page 'Testing the modules involved'
    • Started learning V-Rep and Lua scripting for simulating robot motions.
  • Week 2: 29/05/2017 to 4/06/2017

    • Tested the VL53L0X Lased Distance Measurement sensor, which offers precise distance measurement in a tiny package.
    • Learned Lua scripting for V-REP simulations and also practiced on the V-REP environment to learn basics of it.
    • Detected Wall/Obstacle using proximity sensor and restructured modules to cross it using 4 modules snake in V-REP.
    • Added Wiki page 'V-REP Simulations'
    • Edited CAD files of modules to increase hole diameter to 2mm due to screw unavailability
    • NOTE: Module development delayed due to screw unavailability and also lately facing problems in 3D printer
  • Week 3: 05/06/2017 to 11/06/2017

    • Progress presentation 1 given on 06/06/2017.
    • Interfaced RF Module NRF24L01 and servo MG90S(for the hinges).
    • First Dtto V2 module build completed! Tested crawl motion with existing program.
    • 1.5x4mm screws found, decreased hole diameter for future modules.
    • Started writing program from scratch.
  • Week 4: 12/06/2017 to 18/06/2017

    • Dtto modules 2 and 3 completed!
    • Interfaced the VL53L0X ToF sensor on one of the female faces.
    • Robot halts when it detects and obstacle and continues when obstacle is removed
    • Concluded that motor torque of MG90S is insufficient for most transformations.
  • Week 5: 19/06/2017 to 25/06/2017

    • Progress demonstration on 20/06/2017
    • Added Wiki page 'Building the modules', updated previous pages with more content.
    • Uploaded Arduino code with documentation
    • Edited CAD files and printed few parts for 'Mega Dtto', a scaled up version in order to support high torque servo GOTECK GS-5515MG
    • Started exploring methods to create a virtual Dtto environment for directly programming transformations, and also as a test bench.
  • Week 6: 25/06/2017 to 02/07/2017

    • Module 4 completed!
    • Implemented wheel motion using 4 modules.
    • Completed Virtual Dtto for setting angles, snake motion using Python remoteApi in V-REP.
    • Created poster for project exhibition.
    • Project Exhibition on 30/06/2017
  • Week 7: 03/07/2017 to 05/07/2017

    • Code updated and with better documentation.
    • Created Wiki page 'Wheel Motion: 4 modules' and 'Virtual Dtto'.
    • Created Final Report for project submission.
    • Did some basic testing for the Mega Dtto module.